Friday, November 20, 2015

Relaunch

Our work is done and the boat has been relaunched ready for handover.


Thursday, November 12, 2015

New doors

We've had new doors made at the side hatches and stern and a sliding hatch.

Thursday, October 29, 2015

Tuesday, October 27, 2015

Kitchen

The port side of the kitchen is nearly complete, we're finishing the additional doors which are being made to match the existing doors.



Monday, October 19, 2015

Kitchen

The new worksurface is in on port side and the oven is going in, just about!


Friday, October 16, 2015

Floor

We've laid engineered oak floor throughout the bathroom bedroom and kitchen areas.

The finished bathroom

Dave's done some beautiful work in the bathroom, with details like a lovely curve on the small wall by the toilet and  the porthole liner in sapele contrasting with the ash.




Monday, October 5, 2015

Bathroom progress

The bathroom is transformed by the new white lined shower and toilet installation. Can't wait to see it trimmed up. Photo to follow shortly.

Wednesday, September 16, 2015

Blacking

First job was to jet wash the hull and re-black it.

The brief

We've been asked to do some work on the bedroom and kitchen of this lovely old narrowboat.
We'll reblack the hull, install a bathroom with shower and pump out toilet and refit the kitchen, matching the existing doors. We'll also lay new floor in some areas.